Prepare for Granite Breaking Changes

The Granite upgrade for Boba Sepolia and Boba BNB Testnet will be activated on 1726470000 Mon 16 Sep 07:00:00 UTC 2024.

For Node Operators

Node operators are required to upgrade to Granite before the activation date to avoid chain divergence. For Boba Sepolia and BNB Testnet, the op-node release v1.6.10 and the op-erigon release v1.2.2 contain these changes.

Update to the Lastest Release

Configure the Granite Activation Date

For op-node and op-erigon, the Granite activation date is included in the release, so no action is needed by the operators to configure the node.

For op-geth, the node operator is required to add --override.granite=1726470000 to set up the Granite hardfork.

Verify Your Configuration

Make the following checks to verify that your node is properly configured.

  • op-node , op-erigon and op-geth will log their configurations at startup

  • Check that the Granite time is set to activation-timestamp in the op-node startup logs

  • Check that the Granite time is set to activation-timestamp in the op-erigon startup logs

  • Check that the Granite time is set to activation-timestamp in the op-geth startup logs

Last updated