Prepare for Fjord Breaking Changes
The Fjord upgrade for Boba Sepolia was activated on 1722297600 Tue July 30 00:00:00 UTC 2024. The Fjord Boba Mainnet upgrade will be optimistically activated 1725951600 Tue Sep 10 7:00:00 UTC 2024.
For Node Operators
Node operators are required to upgrade to Fjord before the activation date to avoid chain divergence. For Boba Mainnet, the op-node
release v1.6.8 and the op-erigon
release v1.2.0 contain these changes.
Update to the Lastest Release
op-node v1.6.8
op-erigon v1.2.0
op-geth v1.101315.2
Configure the Fjord Activation Date
For op-node
and op-erigon
, the Fjord activation date is included in the release, so no action is needed by the operators to configure the node.
For op-geth
, the node operator is required to add --override.fjord=1725951600
to set up the Fjord hardfork.
Verify Your Configuration
Make the following checks to verify that your node is properly configured.
op-node
,op-erigon
andop-geth
will log their configurations at startupCheck that the Fjord time is set to
activation-timestamp
in theop-node
startup logsCheck that the Fjord time is set to
activation-timestamp
in theop-erigon
startup logsCheck that the Fjord time is set to
activation-timestamp
in theop-geth
startup logs
Last updated